Move to the cloud without a weekend of guessing

Your applications run on aging servers, a rented rack or one overworked IT manager. We inventory what you have, decide what moves and where it may legally live, then cut over with a rollback plan you have already seen work.

6 to 16

weeks from inventory to cutover, by scope

5

in-Kingdom cloud providers compared

2

rehearsals before the real cutover

Workload inventoryData classificationIn-Kingdom region selectionLift and shiftRe-platformingDatabase migrationLanding zone setupRehearsed cutoverRollback planPost-move tuning

The direct answer

Cloud migration is moving your applications, databases and files from on-premises servers or a hosting provider into a public or sovereign cloud. It suits Saudi companies with aging hardware, rising hosting bills or data that regulators expect inside the Kingdom. We inventory the estate, classify the data, choose the region, move in waves and prove each move before the old system is switched off.

Before and after

What this removes.

Nobody knows what is actually running

Today

The server room holds machines that three different people set up, and no document says which ones the business depends on.

With the system

A written inventory lists every workload, its owner, its dependencies and the order it should move in.

The data may not be allowed to leave

Today

Someone wants to use a cloud region in Europe because it is cheaper, and nobody has checked the classification of the data.

With the system

Each dataset carries a classification, and each one is placed in a region its rules allow.

Last time a move meant a lost weekend

Today

Past upgrades ran over the weekend, broke something on Sunday night and left staff improvising on Monday.

With the system

The cutover is rehearsed twice, timed, and has a rollback you can trigger in minutes.

The cloud bill is bigger than the old one

Today

Workloads were copied as they were, oversized, and now run around the clock at full price.

With the system

We size to measured usage and tag every resource, so the first invoice holds no surprises.

What we build

What lands in your hands.

Estate inventory and dependency map

Servers, databases, integrations, licences and who owns each.

Data classification and region plan

Each dataset matched to a region and a provider your rules allow.

Landing zone

Accounts, networks, identity, logging and guardrails built before anything moves.

Migration waves

Low-risk systems first, critical ones last, each with its own test plan.

Database and file transfer

Continuous replication where possible, so downtime stays in minutes.

Cutover and rollback runbooks

Step-by-step, timed, and rehearsed with your own people.

In depth

How it works, and what to decide.

Choosing what moves, and how

Every workload gets one of four treatments. Rehost copies it as is, which is fastest and keeps the old design problems. Replatform moves it onto a managed database or a managed runtime, which costs a few extra weeks and removes patching work. Refactor rewrites parts of it for the cloud, which only pays off for systems you will keep for years. Retire switches it off, and in our experience a surprising share of an estate falls into this last group once someone asks who still uses it.

The inventory stage decides the split. We scan the servers, read the connection logs and interview the people who rely on each system. The result is a table with one row per workload and a recommended treatment, an effort range and a risk rating. You approve the table before any money goes on infrastructure.

Most mid-sized estates move in three or four waves over 8 to 16 weeks. A single application with one database can move in 4 to 6 weeks including rehearsals. The order matters more than the speed: shared services such as identity and file storage move first, because everything else depends on them.

Data classification, regions and the Kingdom's rules

Saudi Arabia ties where data may sit to what the data is. The Communications, Space and Technology Commission (CST) publishes the Cloud Computing Regulatory Framework, which registers cloud providers and sets obligations by the sensitivity of the customer content they host. The National Data Management Office classifies government and regulated data into levels, and the National Cybersecurity Authority issues cloud cybersecurity controls that apply on top. For the highest levels, hosting has to stay inside the Kingdom.

Personal data adds a second layer. Under the Personal Data Protection Law (PDPL), moving personal data outside Saudi Arabia is permitted only on defined grounds and subject to the transfer regulations issued by SDAIA. Companies often discover this when a SaaS tool or a backup job quietly copies records to a foreign region.

In-Kingdom capacity now exists from several providers, including AWS, Google Cloud, Oracle, STC Cloud and Alibaba Cloud in Riyadh, though the list of services offered differs by provider and changes often. We compare the services you need against each region before recommending one, and we write the classification decision into the project record so an auditor can follow it.

Cutover without drama

A good cutover is boring. We replicate data continuously from the old database to the new one, so on the day the final sync takes minutes. The application is already running in the cloud against a copy, tested by your own staff, before anyone changes a DNS record.

We run two full rehearsals. The first finds the surprises: a hard-coded IP address, a licence tied to a machine, a scheduled job nobody documented. The second is timed against the written runbook, with the people who will be on duty during the real move. If the second rehearsal misses its time window, we do not book the real date.

The old system stays untouched and read-only for an agreed period after cutover, usually 2 to 4 weeks. That is your rollback. When the period ends without incident, we decommission it with a signed checklist, and the savings start for real.

The delivery plan

Five stages. You sign off every one.

Read each stage as a small contract: what we need from you, what lands in your hands, and the sentence that has to be true before we move on.

01 / 05

Discover and classify

2 to 3 weeks

We inventory every workload and dataset, then classify the data and shortlist the regions that may host it.

What you do
  • Give us access to servers and admin consoles
  • Name an owner for each system
  • Share any contracts and licences
What we deliver
  • Inventory with a recommended treatment per workload
  • Data classification record
  • Region and provider comparison
Exit criteria

We move on when you have approved the inventory, the classification and the target region in writing.

02 / 05

Landing zone

2 to 3 weeks

We build the accounts, networks, identity and logging the workloads will move into.

What you do
  • Approve the network and access design
  • Nominate your administrators
  • Confirm budget alerts
What we deliver
  • A working landing zone as code
  • Central logging and backups
  • Cost tags and budget alerts
Exit criteria

We move on when a test workload runs in the landing zone and your administrators can sign in with the agreed roles.

03 / 05

Migrate in waves

3 to 8 weeks

We move systems wave by wave, starting with the least risky and testing each one with your staff.

What you do
  • Test each wave against your own checklist
  • Confirm maintenance windows
  • Report anything that behaves differently
What we deliver
  • Each wave live in the cloud on a copy
  • Test results per system
  • Updated runbooks
Exit criteria

We move on when every system in the wave passes your acceptance checklist while the old one still runs.

04 / 05

Rehearse and cut over

1 to 2 weeks

Two timed rehearsals, then the real cutover with the old system held ready as a rollback.

What you do
  • Staff the rehearsals and the cutover
  • Sign off the go decision
  • Tell users about the window
What we deliver
  • Timed runbook
  • The cutover itself
  • Rollback kept available
Exit criteria

We move on when users are working on the new system and the old one is read-only and unchanged.

05 / 05

Tune and decommission

2 to 4 weeks

We right-size resources against real usage and retire the old environment with a signed checklist.

What you do
  • Review the first cost report
  • Approve decommissioning
  • Collect user feedback
What we deliver
  • Right-sizing report
  • Decommission checklist
  • Handover documentation
Exit criteria

We move on when the old environment is switched off and the monthly cost matches the forecast.

Buyer questions

Asked before signing.

How long does a cloud migration take?

A single application with one database usually moves in 4 to 6 weeks. A mixed estate of a dozen systems takes 8 to 16 weeks in waves. The inventory stage gives you a firm range for your own estate before you commit to the build.

Does our data have to stay in Saudi Arabia?

It depends on its classification and on whether it is personal data. Regulated and government-linked data often must stay in the Kingdom, and PDPL restricts transfers of personal data abroad. We record the decision per dataset, and when in doubt we choose an in-Kingdom region.

Which cloud provider should we pick?

We compare AWS, Google Cloud, Oracle, STC Cloud and Alibaba Cloud against the services you actually use, the regions they offer in the Kingdom, your existing licences and your support needs. We give you a written recommendation with the trade-offs, and the choice stays yours.

Will our systems go down during the move?

For most systems, downtime is limited to the final sync and the switch, which we aim to keep to minutes and schedule outside business hours. Systems that cannot stop at all need a different pattern, and we plan that in stage one.

Do we own the infrastructure code and accounts afterward?

Yes. The cloud accounts are opened in your company's name, and the infrastructure code, runbooks and documentation are handed to you in your own repository. You can run it yourselves, or ask us to operate it under a support agreement.

Ready to move with a plan instead of a hope

Tell us what you run today and where it sits. We will return an inventory approach, a region view and a timeline range within a week.